• 2022 March 22 15:53

    Aker Solutions delivers Njord A platform

    Following several years of extensive upgrades, the drilling and production platform Njord A is ready for handover to Equinor. Towing it back to the field has started today, March 22, according to the company's release.

    The project has provided more than 6,000 man-years in Norway and the Norwegian share of value creation from the project has been around 95 percent.

    Njord A has been described as Norway's largest renovation project. After the contract was signed on March 17, 2017, significant upgrades have been carried out on the hull and the platform deck to extend its lifetime for another 20 years of production.

    "A refurbishment project is never easy, especially at this size and complexity, and with the addition of having to be carried out in the middle of a pandemic with a shortage of labor and a strict infection control regime. This makes me even more proud that we have now reached this important milestone. However, I am most proud that we have carried out this large scope of work at our Stord yard without a single serious injury to either people or material," said Sturla Magnus, executive vice president and head of Aker Solutions' topside and facilities business.

    The upgrade of Njord A has been a project with very high local content in Norway. The engineering was performed mainly by Aker Solutions' offices in Bergen, Stavanger, Fornebu and Trondheim. The construction has been carried out at the company’s yards at Stord and Verdal. Close to 400 different supplier companies have been involved in the project, most of them Norwegian.

    "Njord A is now ready for several decades of energy production and value creation for the greater society. The project has had significant ripple effects, contributing to a lot of activity both for Aker Solutions and a large number of supplier companies which in various ways have contributed to the project," said Magnus.

    The Njord A contract was a groundbreaking undertaking in the Norwegian oil and gas industry when it was originally signed in 2017, being the first time a production platform on the Norwegian continental shelf was transported to shore for complete overhaul and upgrades. This has been reflected in terms of the increased scope and duration of the project during the project period. In 2018, an additional contract was awarded to Aker Solutions to prepare the platform for receiving oil and gas from the Fenja field, which entailed additional manufacturing and installation work on the platform. The company has also been tasked to assist Equinor in the offshore hook-up work preparing it for the start of production in the fourth quarter of 2022.

    Njord A was originally delivered by Aker Solutions in September 1997. The platform deck was manufactured and assembled at the Stord yard, while the hull was constructed at the Verdal yard. Njord A was the first EPC contract on the Norwegian continental shelf following the implementation of the NORSOK standard in the mid-90s.

    In recent weeks, the platform has been in Klosterfjorden on the west coast of Norway, conducting various sea trials.

    "The sea trials are now complete, and we are on schedule for delivery and tow out to the field. Compared to the original version of the platform delivered in 1997, it is a quite different platform that is now ready to be transported back to the Njord field. Hardly any part of the platform has remained untouched, and the total dead weight has increased by 23 percent. The upgrades on the hull have increased the platform's buoyancy by 24 percent, and the payload capacity on the platform deck has increased by 31 percent," said Carl van der Hagen, project director at Aker Solutions, who was also involved in the construction of the original platform in the 90s.





2024 May 4

13:47 HD Hyundai, ABS to set standards for e-propulsion ships
12:08 Australian Govt selects BAE Systems and ASC to build sovereign nuclear powered submarines
10:51 Van Oord’s heavy lift installation vessel undergoes upgrade

2024 May 3

18:00 Holland America Line begins pilot test of renewable fuels on its flagship, Rotterdam
17:20 European Hydrogen Bank auction provides €720 million for renewable hydrogen production in Europe
17:06 GTT and PipeChina Innovation sign a License Agreement for the use of GTT membrane containment technology for onshore LNG storage
16:43 CMA CGM to launch M2X - Mexico Express Service connecting Far East to Mexico
16:31 Wartsila to supply the engines for a new Canadian Coast Guard Polar Icebreaker
15:58 The Port of Long Beach celebrates “Tri-gen” system for producing renewable hydrogen, electricity and water
15:06 Astrakhan region ports’ cargo volume in Q1, 2024 soars 78%
14:32 Valenciaport participates in a European project to promote the use of renewable energy for self-consumption in the port
13:50 Seatrade reaches settlement with Dutch Public Prosecution Service
13:15 Dennis Tetzlaff appointed Chief Operating Officer Fleet at Stena Line
12:40 ONE releases financial result for FY2023
12:20 IMO biofouling project to address biodiversity threat extended
11:30 Corvus Energy to supply ESS for the first net zero subsea construction vessel
11:10 Damen launches fully electric RSD-E Tug 2513 for Port of Antwerp-Bruges
10:30 Port of Rotterdam reduces CO2 emissions by 10% in 2023
10:02 HD KSOE wins $286mn order for four MGCs
10:00 Russian seaports in Q1, 2024: Infographics and Analytics
09:00 HD Hyundai Heavy secures contract to build LNG carrier duo

2024 May 2

18:07 World’s most environmentally friendly tug fleet delivered to HaiSea Marine
17:38 SOHAR Port and Freezone sings agreement with METCORE for Mass Flow Meter Implementation
17:23 Unifeeder launches China Gulf Express
16:59 Allseas receives T&I contract for Gennaker offshore wind farm
16:30 CMA CGM’s newest container vessel visited the HHLA TK Estonia terminal
15:46 DP World introduces new rail route from China to Turkey
14:32 Hybrid technology to optimise energy use and cut emissions for Matson Navigation Company’s new LNG-powered container ships
13:54 Bureau Veritas awards AiP for TotalEnergies’ Skipe V2 tool
13:24 Hapag-Lloyd launches first dry container tracking product “Live Position”
12:58 Europe’s ports have €80 billion investment needs for the next 10 years
12:15 MABUX: Bunker Outlook, Week 18, 2024
11:42 APSEZ FY24 net profit jumps 50%
11:19 Tristar Eships to manage its carbon footprint with Wartsila’s Decarbonisation Services
10:48 Topsoe awarded contract to support FEED study for new low-carbon ammonia plant in Louisiana, US
09:26 Maersk posts Q1 2024 results

2024 May 1

17:13 Matson picks Kongsberg Maritime's hybrid technology for its new LNG-powered container ships
16:22 All American Marine delivers hydrofoil-assisted tour vessel to Phillips Glaciers
15:24 Corvus Energy to supply ESS for the first Net Zero Subsea Construction Vessel
14:02 Stena Line taps Dennis Tetzlaff as Chief Operating Officer Fleet
12:31 APSEZ secures AAA Rating – India’s first private infrastructure developer with AAA
11:57 Unifeeder continues its expansion in Latin America
10:09 IMO's Legal Committee finalizes new guidelines on seafarer criminalization

2024 April 30

16:14 LR grants AiP to H2SITE’s AMMONIA to H2POWER technology
15:17 IRS partners with MARIN to enhance technical expertise in shipbuilding
13:42 Allseas T&I contract for Gennaker offshore wind farm
12:03 CSSC and QatarEnergy sign agreement for construction of 18 Q-Max class LNG carriers
10:13 First ship departs Baltimore through limited access channel

2024 April 29

17:42 Abu Dhabi leaps a staggering 10 places in 2024 LMC Report
16:19 Norwegian engine builder Bergen Engines joins FME MarTrans initiative
15:13 Hitachi, Chantiers de l’Atlantique to seal French offshore substation contract
14:53 Port of Greenock given vote of confidence with new Türkiye container service
14:09 Aker Solutions ASA:announces first quarter results 2024
13:37 Gasum Group's Q1 sales volumes rose 73% due to higher natural gas volumes
12:14 New Zealand cruise market on track for recovery
11:40 Vitol announces satisfaction of a condition precedent relating to the golden power proceeding
10:41 JERA Energy India begins operations as JERA’s base of operations in the country

2024 April 28

15:13 IACS publishes new recommendation for conducting commissioning testing of BWMS
14:11 Skanska set for South Brooklyn Marine Terminal Buildout (SBMT)
12:27 Philly Shipyard and HD Hyundai Heavy Industries sign MoU
12:03 Equinor to commence second tranche of the 2024 share buy-back programme
10:16 Gebrüder Weiss enlarges logistics center in Budapest
09:37 Opening of MARIN's Seven Oceans Simulator centre (SOSc) in the Netherlands slated for May 2024

2024 April 27

16:36 National Transportation Safety Board: Undetected flooding from a through-hull pipe led to capsizing of dredging vessel
15:49 Chantiers de l’Atlantique picks Brunvoll propulsion for the world’s largest sailing ships
14:31 US Navy announces first MCM MP embarked on USS Canberra
13:42 Interim president Michelle Kruger takes helm at Austal USA
12:17 DEME annnounces start of share buyback program
10:28 Ships with Korean-made LNG containment face key supply chain disruptions

2024 April 26

18:04 Seaspan celebrates 30 years of ship repair in Victoria