    Damen Shiprepair Amsterdam completes major modification works on the Sea Installer

    Damen Shiprepair Amsterdam (DSAm) has concluded major modification works on the Sea Installer. The principle scope of work involved the extension of the main crane boom, giving the A2SEA-owned offshore wind farm installation vessel increased reaching capacity: a pertinent point considering the trend of the increasing size of offshore wind turbine components. Other work comprised structural modifications as a consequence of the larger crane.

    DSAm, part of Damen Shiprepair & Conversion, began the work by removing all crane-related components including the boom, boom rest, A-frame, winch and hook block pockets from the vessel. A2SEA supplied the new A-frame and boom extension. Niron Staal, also part of Damen Shiprepair & Conversion, supplied the new boom rest, hook block pockets, trolley rail and support stools.

    The crane boom was lengthened by inserting the new extension. The fact that all elements were composed of high tensile S690 steel had its consequences to the timing of the project. Damen Junior Project Manager Remco van Dam informs: “This material requires distinct and carefully planned procedures. You can cut it when it’s cold, but, before you weld it, you need to heat it with heating elements to 200°C to remove any traces of water.”

    “Then, after slight cooling, the welding itself needs to take place at the correct temperature in a protected environment. For this, we constructed air-tight welding tents.”

    Once complete, the weld in question was cooled prior to non-destructive testing after 48 hours. “We also performed our own initial checks after 24 hours in case any additional welds were needed. The main point with S690 is that you cannot rush things. If you go too fast, it can set you back 3 days.”

    The configuration of the upgraded crane is such that it can be operated in two modes: a long mode with the crane boom extension in place, and a short mode with the extension removed. The Sea Installer now has a flexible crane capacity of 900 tonnes in short mode and 700 tonnes in long.

    Two mobile Mammoet cranes lifted the extended crane boom back onto the vessel. To create a stable lifting foundation – allowing for a maximum of 0.3 degrees of tilt – the quayside was levelled prior to the vessel’s arrival at the yard. This required laying no less than 800 cubic metres of sand, topped off with 750 dragline crane mats.

    Installing the larger crane on the Sea Installer had numerous implications on existing on board structures. The boom rest had to be replaced, which in turn necessitated additional modifications to the accommodation area. In order to house the main hook and auxiliary hook in both long and short mode, the existing auxiliary hook block pocket was replaced with a new construction that comprised one main and two auxiliary hook block pockets.

    The bigger crane also needed a bigger winch: DSAm replaced the existing winch with a larger, 900-tonne capacity, winch. This included all the necessary adjustments of the electrical, hydraulic and cooling systems. The vessel’s main mast also needed structural modifications.

    With the 132-metre long vessel at the yard, DSAm also executed various standard maintenance jobs such as painting, pipe renewal and thruster inspection.

    As is standard working practice at DSAm, safety issues were top of the agenda for yard personnel and the vessel’s crew, who remained on board throughout the modification works. Daily meetings commenced with discussion of safety issues and heavy lift events were given special attention in so-called ‘tool-box’ meetings.

    The smooth running of the entire project was facilitated by the joint efforts of the DSAm and A2SEA personnel. “It has been a pleasure to work with the ship’s crew,” concludes Mr Van Dam. “There has been good communication throughout and this has helped us in many ways. For example, their involvement in adjusting the ship’s ballast tanks during such a heavy lift was crucial.”




2024 April 26

18:04 Seaspan celebrates 30 years of ship repair in Victoria
17:31 HMM enhances maritime safety with AI technology
17:13 Potential Strait of Hormuz closure threatens 21% of global LNG supply - Drewry
16:42 Van Oord christens two new hybrid water injection dredgers and an unmanned survey vessel in Rotterdam
15:57 CMA CGM announces FAK rates from Asia to North Europe
15:24 MOL announced delivery of LPG dual-fuel LPG/ammonia carrier Aquamarine Progress II
14:53 DP World and Asian Terminals launch new Tanza Barge Terminal in Cavite
14:23 MH Simonsen orders eight hybrid methanol dual-fuel tankers at China’s Jiangxi New Jiangzhou Shipbuilding
13:47 DP World and Malaysia’s Sabah Ports form a partnership to manage Sapangar Bay Container Port
13:22 SCHOTTEL to equip Guangzhou Port Group’s latest e-tug with two RudderPropellers type SRP 360
12:57 FESCO Group proposes a mechanism in favour of Russian logistics operators over their foreign competitors in domestic transport market
12:39 SSK shipyard launches the Project 14400 support ship Nikolai Kamov in the Nizhny Novgorod region
12:33 Six companies start a joint study for the establishment of an ammonia supply chain based in the Tomakomai area of Hokkaido
11:52 European shipowners welcome 40% production benchmark for clean shipping fuels in Europe
11:14 Greek shipowners leaders in the secondary market once again
10:08 MPCC secures ECA-covered sustainable financing for its dual-fuel methanol newbuildings
09:38 Romanian port of Constantza to receive a new oil products terminal

2024 April 25

18:07 MSC collaborates with GSBN to trial integrated safe transportation certification verification process
17:23 China launches construction of cutting-edge marine research vessel
17:06 CMA CGM and Bpifrance launch €200mln fund to decarbonize French maritime sector
16:46 Avenir LNG orders two 20,000 M3 LNG bunker delivery vessels
16:05 Port of Amsterdam revenues up to €190.4 million in 2023
15:46 OOCL launches Transpacific Latin Pacific 5 to offer express linkage between Asia and Mexico
15:23 MOL is 1st Japanese shipping company to raise funds through transition linked loan using performance-based interest subsidy system
14:53 Trident Energy enters the Republic of Congo with strategic deal
14:21 LNG-powered ship moored in Koper for the first time
13:38 MABUX: Bunker Outlook, Week 17, 2024
13:32 The Grimaldi Group's Great Abidjan delivered in South Korea
13:12 European Parliament updates trans-European transport network guidelines
12:40 ClassNK releases route correction factors calculation tool "WACDAS"
12:10 MOL and Gaz System enter into agreement on FSRU project in Gdansk, Poland
11:31 Wartsila Gas Solutions to supply cargo handling system for a new 12.5k LNG bunkering vessel for Scale Gas
11:09 Wartsila secures China’s largest-ever methanol newbuild order
10:42 Valencia port community increases waste recovery by 75%
10:22 Kongsberg completes factory acceptance testing of the first production long-range autonomous underwater vehicle system HUGIN Endurance
09:53 Vladimir Putin: The BAM carrying capacity to reach nearly 42 million tonnes in 2024
09:47 Hanwha Ocean reports an operating profit of $38.6 mln on a consolidated basis in January-March 2024

2024 April 24

18:02 Incat to commence design study for new electric-hybrid ferry in partnership with DFDS
17:39 FESCO's 2023 revenue was up 6% Y/Y to RUB 172 billion
17:20 Peninsula adds chemical tanker Aalborg to supply in the Port of Barcelona
17:17 NCSP Group’s Q1 net profit rises 1.9 times to RUB 4.8 billion
17:03 AtoB@C Shipping reveals names for the rest of its new hybrid vessels
16:45 Red Sea conflict brings massive carbon emissions increases in ocean freight shipping
16:17 Wallenius Wilhelmsen signs a 20-year lease agreement with the Georgia Ports Authority
15:46 AD Ports Group secures a 20-year agreement to operate and upgrade Luanda multipurpose port terminal in Angola
14:43 Hengli Heavy Industries receives an order for four bulkers from Ciner Shipping
14:27 TotalEnergies, OQ to launch $1.6bn LNG bunkering project in Oman
13:54 Major shipping companies may resume limited calls to the Port of Baltimore
13:10 HD HHI inks MOU with Philly Shipyard for US vessel MRO business
12:45 MSC adds King Abdul Aziz Port in Dammam to its East Africa Express service
12:16 Norton Rose Fulbright advises Citibank on $450m facility for Danaos Corporation to acquire eight newbuild vessels
10:40 DEME and Jan De Nul build the foundation for an energy island on behalf of Elia Transmission
10:08 Salzgitter AG and Uniper SE sign pre-contract for the supply and purchase of green hydrogen
09:18 Norwegian Cruise Line and Fincantieri float out the first ship of the extended Prima Plus Сlass

2024 April 23

18:02 SFL acquires two LNG dual-fuel chemical carriers in combination with long term employment
17:31 Pioneering Spirit completes its first pipeline pull-ins in Kalsto, Norway
17:04 Valenciaport admits the four bids for the construction of the North Terminal
16:54 Vancouver welcomes its first resident battery electric tugs
16:24 Shanghai Port and Lianyungang Port strengthen partnership
15:44 WinGD to debut short-stroke engine design after successful shop test
15:24 Overseas Shipholding Group awarded federal grant to design marine transport for liquified CO2 captured by Florida’s largest emitters
14:53 H2Carrier to establish Norway's first integrated PtX and wind power project
14:23 IBIA and BIMCO sign collaboration deal
13:52 Container ship Xin Xin Shan arrested in Singapore
13:22 MOL to merge its subsidiaries in the Philippines
12:53 Haiti fuel terminal operations halted as gangs seize trucks
12:30 HHLA acquires interest in Austrian intermodal service provider Roland
11:42 South Korean yards built 500 LNG carriers for export in 30 years
11:19 Wartsila to provide a range of solutions for the six PCTCs being built for Sallaum Lines
10:36 Thecla Bodewes Shipyards successfully launches 'Vertom Anette’ for Vertom Group