• Home
  • News
  • Main phase of Beloomut hydro engineering system rehabilitation project to be completed by the end of 2019, Moscow Canal authority says
  • 2019 August 19 16:11

    Main phase of Beloomut hydro engineering system rehabilitation project to be completed by the end of 2019, Moscow Canal authority says

    A bidding process has been announced for the development and implementation of the comprehensive project “Reconstruction of Infrastructure Facilities of the Moscow Canal. Phase 2. Reconstruction of Beloomut waterworks. Sub-stage 4", the Moscow Canal press office told PortNews. The Moscow Canal authority plans to select a new general contractor for the completion of construction and installation works in Belomut. Maximum price of the contract is RUB 477,657,958,310.

    If the e-tender takes place and all the procedures for evaluation of bidders applications and summing up the results are completed within the scheduled time, then the conclusion of the state contract with the new general contractor may take place on September 10, 2019. In this case, according to the requirements of the Federal Law “On the contract system in the procurement of goods, work, services to meet state and municipal needs” (dated 04/04/2013, No. 44-FZ), the winner in the tender who will be awarded the contract must begin to fulfill its obligations within 30 days, that is, in the first decade October 2019.

    The main construction and installation works at Beloomut hydroelectric complex, according to the tender documentation, are planned to be completed before the end of 2019. By this time, the general contractor the main dam structures are to be erected, power and control cables for power supply will be laid, and the installation of an automated process control system (APCS) and outdoor lighting system will be completed.

    In addition, builders must finish work on the new lock and at the offices and facilities complex. It is necessary to fill the site with sand, equip access roads, improve the territory, commissioning of the engineering networks and new administrative building.

    Construction and installation work as part of the Oka River Beloomut hydroengineering system rehabilitation was canceled April 9, 2019 due to the bankruptcy of the then general contractor - FSUE ATEX. By that time, 13,the commissioned a year earlier new lock of the system 13.5 thousand vessels passed through the new lock of the hydroelectric station commissioned a year earlier.

    The Moscow Canal is the largest water transport and water management complex, and acts as the inland waterways public authority in 12 constituent entities of the Russian Federation. The MC facilities include 235 hydraulic engineering structures and 3842 km of waterways.

    The Beloomut hydroengineering system was built on the Oka River along with the Kuzminsk hydroengineering complex in 1911-1915 to the design developed by Russian engineer Nestor Puzyrevsky. In 2015, the facility rehabilitation project kicked off. The Customer of the project is the Federal Agency for Maritime and River Transport of Russia, the developer is the Moscow Canal. The project General Designer is Aquatic JSC. The Belomut redevelopment will help solve the problem of shallow water in the Oka River. The new dam should gradually increase the controlling depths by 76 cm and, thus, ensure smooth transits of passenger and cargo vessels. According to the state assignment, Moscow Canal authority maintained controlling depths in the section of inland waterways (on the Oka River from the Beloomut hydroelectric complex to the settlement of Shchurovo and further from the mouth of the Moscow River to the Severka hydroelectric facility) at around 1.7 meters.

    The project of comprehensive rehabilitation of the Belomut, involving the construction of a new water development complex, was launched in 2015. Then a state contract was signed with the General Contractor for construction and installation works worth RUB 5.54 billion rubles. The contract was awarded to ATEX company that was selected in the tendering process.
    According to the new state contract, before January 1, 2019, a modern shipping lock, a permanent dam, automated control system, office and industrial buildings, as well as a water intake unit with two artesian wells and a water treatment system, were to be built on the territory of the old hydroelectric complex.

    In 2017, the first phase of the system rehabilitation was completed, which included the construction of a shipping lock and the first phase of the dam. In 2018, it was planned to complete the dam, the system of transport safety and monitoring of engineering, as well as to carry out landscaping of the territory of the hydroelectric complex and dismantle the old hydraulic structures.

    As the General Contractor encountered financial problems the Beloomut project was not completed on time. Construction and installation work continued until the end of March 2019. By that time, the construction of a new dam was completed, and the entire reconstruction was 90% complete. The work was stopped for the period of 2019 spring flood 2019 and the rehabilitation project was put on hold.

    On October 11, 2018, the Moscow City Arbitration Court initiated a monitoring procedure in relation to the ATEX in the framework of the bankruptcy case of the enterprise. In April 2019, a bank guarantee expired, which was a guarantee of fulfillment of the obligations of ATEX to Moscow Canal under the Beloomut contract. Thus, there were risks of not repaying the outstanding advance payment and writing off other payments to ATEX'S creditors. The reconstruction project of the hydroelectric complex could remain without financing and turn into a never-ending construction project.

    In order to prevent serious financial losses and long-delayed construction in Belomut, on April 9, 2019, in accordance with the requirements of the law, the contract with FSUE ATEX was unilaterally terminated. Thanks to the actions of the Moscow Canal to implement a bank guarantee and penalties imposed on ATEX, the federal budget received RUB 326.8 million, including RUB 179.4 million as fines and RUB 147.36 million as advance payment not fully reimbursed.

    The change of general contractor and the postponement of the completion of the Belomut reconstruction do not affect smooth operation and condition of the facilities. All main elements of the hydraulic engineering system are fully functioning. The old dam works properly, which maintaince the required water level. The new commissioned lock has been operating since the 2018 navigation season. The lock has successfully withstood two floods and has served the second shipping season now.




2022 January 27

18:35 ABP launches the first of its new tranche of port-manufacturing sites at Port of Hull
18:05 Indian Register of Shipping classes first 100 pax hybrid catamaran (battery powered) ferry
17:52 Onezhsky Shipyard launches lead crab catching ship built for Russian Crab Group
17:35 Kawasaki Heavy Industries announces delivery of LPG-fueled LPG carrier CRYSTAL TRINITY
17:05 NAPA and MOL roll out digital Navigational Risk Monitoring Solution on over MOL’s 700+ ships
16:45 Port of Antwerp, North Sea Port Flanders and Port of Zeebrugge launch the stimulus programme ‘Accelerating modal shift’
16:36 Construction of digital shipyard commenced at Onezhsky Shipbuilding, Ship Repair Yard
16:17 Suez Canal Economic Zone signs local and foreign contracts for Sokhna port new berths works
15:35 Construction of support fleet base in Ust-Luga approved by Glavgosexpertiza
15:32 ABS grants AIP to a coordinated design for a wind turbine installation vessel
15:14 Tarragona Port Authority has awarded Global Ports Holding a 12-year concession to manage the services for cruise passengers
15:00 Marine Rescue Service removed all oil products from Chinese ship Xing Yuan
14:53 Cooperation Agreement signed between ThPA S.A. and Suez Canal Economic Zone
14:42 DP World joins forces with Mærsk Mc-Kinney Møller Center for Zero Carbon Shipping
14:32 A.P. Moller - Maersk shares millions of weather observations to aid climate science
14:22 IMB releases 2021 Piracy and Armed Robbery Report
14:04 FESCO launches regular container train from Vladivostok to Ulyanovsk
13:40 Swissterminal starts a new rail link between the port of Antwerp and Ottmarsheim
13:28 FESCO confirms compliance with standards for operation of vessels in US waters
13:03 Georgia Ports Authority tops 5.5M TEUs, 650K units in 2021
12:49 NYK delivers methanol-fueled chemical tanker
12:02 Throughput of Yeisk port in 2021 remained flat, year-on-year
11:30 Tallink Grupp’s vessel Baltic Queen heads to Naantali, Finland for regular dry-docking
10:56 Throughput of Temryuk port in 2021 rose by 10.3% YoY
10:37 MABUX: Bunker Weekly Outlook, Week 04, 2022
10:33 Haldor Topsoe becomes member of Hydrogen Council to promote green hydrogen solutions
09:48 Registration is underway for 5th Hydraulic Engineering and Dredging Congress
09:29 Baltic Dry Index as of January 26
09:12 Crude oil prices decrease on reduction of supply disruption risks
08:57 MABUX: Global bunker market to continue firm upward evolution on Jan 27

2022 January 26

18:06 Safe Bulkers announces agreement for the acquisition of one Capesize class dry-bulk Japanese vessel
17:54 Olga Naumova takes helm of Russian Fishery Company
17:41 Shearwater GeoServices awarded Western Australia multicomponent surveys by Santos
17:26 Heerema wins decommissioning contract for multiple Petrogas platforms
16:27 USCG to break ice along Penobscot, Connecticut, and Hudson Rivers
16:03 Deltamarin signs an engineering contract for Höegh Autoliners Aurora Class PCTCs
15:58 Avenir sells the world’s largest LNG bunker vessel
15:55 Rosmorport supports "Soul of the Caspian" expedition aimed at studying and conserving Caspian seal
15:33 Maersk Supply Service launches new venture company to deliver offshore vessel charging
14:40 Throughput of OTEKO Group terminals in Taman surged by 82%, year-on-year
14:13 Fincantieri’s U.S. shipyards join Green Marine
13:48 Yakutia LNG project may need new port facilities in Sea of Okhotsk
13:27 Konecranes provides 17 Automated Rubber-Tired Gantry Cranes in fully integrated solution for Port of Felixstowe
12:37 Freeport of Ventspils handled over 11.1 million tons of cargo in 2021
12:01 DNV selected to lead “pioneering" ammonia bunkering safety study in Singapore
11:32 Superyacht Phi delivered to ABS class
11:23 Smart Ports Russia 2022 to bring together ports and terminals in Moscow
10:58 KN transhipped the first bulk bitumen to a tanker
10:58 Port Houston annual TEUs set record with 15 percent growth
10:37 CIMAC World Congress is postponed to June 2023
10:01 Klaipeda Port handled 45.6 million tonnes of cargo in 2021
09:53 KCC signs pilot agreement for Yara Marine’s ‘FuelOpt’ energy efficiency system
09:39 Baltic Dry Index as of January 25
09:18 Crude oil prices start decreasing
08:33 MABUX: Global bunker market compensates losses from the day before

2022 January 25

18:10 Ports of Los Angeles & Long Beach postpone Container Excess Dwell Fee
17:55 Joint Russian-Chinese naval exercise Peaceful Sea-2022 took place in the Arabian Sea
17:36 Broad scope of Wärtsilä power solutions selected for gas-fuelled ferry trio
17:26 ICTSI's Cavite Gateway Terminal beefs up operations
17:04 BLRT Grupp is constructing a unique floating exhibition centre for Norway