    Second stage of construction work at Krievu Island Terminal is approaching the finish line

    The second stage of construction work at the Krievu Island Terminal is almost complete. According to statement of the Freeport of Riga Authority, work progress was confirmed by the Freeport of Riga board members during an on-site visit earlier today. Construction of all additional infrastructure performed by the Freeport of Riga Authority in the territory of the Strek SIA stevedoring company is 100% complete and constructions have been put into service. Construction work in the territory of the other stevedoring company, Riga Coal Terminal SIA, is also done and the object is put into service. Harmonising of the executive documentation is also in progress, which will be finalised in the second half of December.

     “Today we checked that there are no technological obstacles to transfer dry bulk operations from the right bank of the Daugava River – the territories of Andrejsala and Eksportosta – to Krievu Island, which is one of the most modern multi-functional terminals in the Baltic Sea region. The relocation of dry bulk handling technologies to the new terminal is actively taking place, demonstrating the successful start of the transfer process. The removal of coal cargo from Andrejsala and Eksportosta will commence in the near future, and within the next few months coal will all be in the past,” claims the chairman of the board of the Freeport of Riga, Andris Ameriks.

    During the second stage of the Krievu Island project construction of all communications has been completed, including electric supply cables, water supply and sewage systems, as well as the construction of cargo platforms and railway. Concrete-slab and asphalt cover has been constructed for cargo platforms. In the interest of observing environmental protection requirements and protecting the quality of life for those living in urban areas adjacent to Krievu Island, a windbreak fence, 23 metres high and over 2 km long, has been built. The most important function of the windbreak fence is to effectively dampen the effects of dominating winds on the coal piles, preventing coal dust from blowing into the air and ending up in the environment.

    The stevedoring companies are building administrative and process buildings as well as supplying and installing special-purpose equipment for coal handling, crushing, transportation and loading onto ships. The adjustment of settings for the installed technological equipment and the preparatory work to start the transhipment of coal have already begun. The work by the stevedoring companies in the territories will be fully completed by the end of this year.

    “We are pleased that all parties involved in the project, both stevedoring companies and construction workers, have been able to meet their obligations and deadlines which, of course, required a great deal of effort by everyone. Nevertheless, the result is well worth it.  The Krievu Island Terminal is ready for its launch, and soon the first coal cargoes will arrive here,” said Ansis Zeltiņš, CEO of the Freeport of Riga.

    To free the centre of Riga from coal cargo and transfer the handling of coal to the new terminals equipped with modern technologies on Krievu Island, in 2012 the Freeport of Riga Authority commenced the project Development of Infrastructure on Krievu Island for the Transfer of Port Activities from the City Centre. On 31 December 2015, the construction of the principal infrastructure of the Krievu Island Terminal was completed, which included 4 deep-water piers (15.5 m) with the combined length of 1,180 metres and the necessary access road and utility infrastructure.




2024 March 29

13:40 HD KSOE and Infineon sign MoU to develop ship electrification technology
13:29 NYK and JMU formulate method for evaluating ship performance in actual seas
12:59 HD Hyundai wins US$463 mln warship order in Peru
12:09 COSCO SHIPPING Ports throughput up by 4.4% YoY to 135,808,554 TEU in 2023
11:46 The "Ane Maersk" calls at the Eurogate container terminal in Hamburg for the first time on its maiden voyage from Asia to Europe
11:20 Sallaum Lines and Fujian Mawei Shipbuilding commence construction of Ocean Class vessels
10:43 Oasis Marine develops solutions for offshore hydrogen bunkering
10:03 Petrofac secures contract extension with ONEgas West in the UK market

2024 March 28

18:05 Jan De Nul, ENGIE and Equans launch a pilot project centred around the use of Vanadium Redox Flow batteries
17:35 Latvian port equipment manufacturer Bleste introduces new bulk handling ‘bucket’
17:05 Investors upgrade Navios Maritime Partners
16:25 DEME reports 22% increase in the orderbook and a record-high turnover of 3.3 billion euros in 2023
16:14 MABUX: Bunker Outlook, Week 13, 2024
15:41 AD Ports Group announced the opening of Saadiyat Marina & Ferry Terminal and Rabdan Marina
15:11 Sydney invests $11.5 million in two new operational vessels designed by Incat Crowther
14:55 China’s Jinzhao wins Peru $405m port construction contract
14:13 APM Terminals Moín handled six million TEU
13:48 ClassNK grants Innovation Endorsements for Products & Solutions to two innovative initiatives by MOL
13:37 Konecranes launches its flagship Konecranes X-series industrial crane
12:53 United European Car Carriers UECC spearheads collaboration with industry leaders to advance CNSL as a sustainable marine fuel
12:26 Ocean Network Express announces Transpacific service
11:48 Yang Ming announces 2025 Trans-Pacific service network
11:24 Fincantieri signs contract for the supply of two PPAs to Indonesia
10:42 Maersk transported more than 660,000 TEU using clean fuel in 2023
10:23 Documentation delays push industry costs to $3bn
09:48 PONANT and FARWIND Energy partner to develop green hydrogen refueling solutions

2024 March 27

18:22 Bureau Veritas awards world’s first prototype certification for SolarDuck’s floating offshore solar solution
17:58 The recently converted Allseas's shallow water pipelay barge starts preparations for its first commercial project
17:38 The Port of Rotterdam calls on the European Commission and Parliament to focus on actively promoting green energy
15:23 SEFE to become sole shareholder of WIGA
14:53 Ocean Installer secures yet another SLM contract with Equinor
14:23 Cadeler signs offshore wind turbine installation contract for the vessel Wind Scylla
13:42 Carnival Cruise Line orders 5th Excel-class cruise ship
13:11 Maersk and MSC overcharging cargo owners for EU ETS, says T&E
12:52 The Port Authority of Valencia launches the ZAL project in the Port of Valencia
12:11 Clarkson Port Services and Peak Group collaborate to deliver Port Agency services across the North Sea
11:42 Wan Hai Lines holds ship naming ceremony for new vessels
11:24 Consolidated shipping lines EBIT loss was $1.44 billion in Q4 2023: Sea-Intelligence
10:49 Seaspan Shipyards receives long-term contracts for the pre-construction work of the the Canadian Coast Guard's first six multi-mission vessels
10:14 Woodside completes sale of 10% scarborough interest

2024 March 26

18:02 COSCO Shipping Lines introduces new Americas service
17:30 Davie awarded first contract for design of icebreaker fleet under Canada’s National Shipbuilding Strategy
17:04 Sanctions complicate Arctic LNG ship sales, Hanwha Ocean says - Bloomberg
16:57 Terntank places an order for 1+1 additional wind/ methanol-ready hybrid tanker
16:28 BW LNG completes acquisition of two TFDE vessels from Stena Bulk
15:50 Hanwha Ocean develops VR-based special vehicle simulator
15:20 TotalEnergies and SINOPEC join forces to produce sustainable jet fuel at a SINOPEC's refinery
14:52 Wärtsilä Lifecycle Agreement to guarantee operational reliability of new wind farm installation vessel
14:23 Hudong-Zhonghua launches two LNG carriers
13:51 Cargo ship hits Baltimore’s Key Bridge
13:12 Final sanctioned tanker with Russian Sokol oil to reach China port - Reuters
12:42 Adani Ports acquires 95% of Odisha's Gopalpur Port from SP Group for $162 million
12:21 IHI and Yara Clean Ammonia agree to jointly assess clean ammonia business collaboration
11:41 Yara Clean Ammonia and Azane granted safety permit to build world's first low emission ammonia bunkering terminal
11:16 Wartsila and Royal Caribbean Group celebrate 15 years of collaboration on digital transformation
10:46 A global carbon tax on shipping is coming, says ABS Chairman and CEO
10:21 Eni, Fincantieri and RINA establish partnership for maritime transport decarbonization

2024 March 25

18:07 The Maritime and Port Authority of Singapore continues to investigate reports of oil spills off the port of Tuas
17:31 “K” Line, NIPPON HAKUYO and OPT Gate sign an agreement for a new fire detection system for car carriers
17:07 Greek merchant fleet recorded slight decline in January 2024
16:47 Hanwha Ocean Plans to develop green technology and naval ships
16:25 U-Ming Singapore and ITOCHU sign milestone MoU for the joint development of ammonia dual-fuel and de-carbonized vessels
15:34 Svitzer targets methanol-fuelled MAN 175DF-M engine for tug application
15:04 Wallenius Wilhelmsen signs contracts for four 9,300 CEU vessels with China Merchants Jinling Shipyard
14:40 Taiwan International Port to upgrade terminal facility at Kaohsiung
13:59 Сruise ship Carnival Freedom catches fire near Bahamas
12:59 Hanwha Ocean wins 2.4 tln-won order for 8 LNG ships
11:16 Inland Ports meet in Paris to talk about the innovation potential of inland ports
10:50 IMO agrees possible outline for maritime “net-zero framework”
10:24 Hapag-Lloyd to continue to avoid the Red Sea route