• 2018 June 26 10:30

    Crucial progress in construction of the second stage of the Krievu Island Terminal

    Last week, on 20th of June, Ansis Zeltiņš, CEO of the Freeport of Riga, and representatives from ACB, general contractor for the construction of the second stage of the Krievu Island Terminal project, familiarised Members of the Freeport of Riga Board with the progress in the construction of the second stage of the Krievu Island project during an on-site visit. Freeport of Riga says members of the Board gained confidence that the construction of additional infrastructure would be carried out according to the work plan and more than half of the total construction work had been completed in the territories of stevedoring companies.

    “What we saw today strengthens our confidence that the principal goal of the Krievu Island project will be successfully achieved, and the complete transfer of bulk cargo operations from the right shore of the Daugava — Andrejsala and Eksportsala territories — to Krievu Island will be carried out as planned. The handling of cargo in one of the most advanced multi-functional terminals in the Baltic Sea Region will start as planned — in 2019”, Andris Ameriks, Chairperson of the Freeport of Riga Board, highlighted.

    So far within the framework of the second stage, the construction of the gas pipeline and other underground communications, as well as platforms and railway, has been completed. Works on Krievu Island are being carried out according to the planned schedule of construction works. For example, the construction of power supply cables has practically been completed in the territory of SIA STREK, whereas work on the construction of a water supply system are being actively carried out in the territory of SIA Riga Coal Terminal. Concrete-slab and asphalt cover is currently being constructed for cargo platforms. Stevedoring companies at the site are installing technological equipment and constructing automatic wagon supply systems. The stevedoring companies will install mobile technological equipment for handling cargo. Likewise, works are being carried out on construction of a wind-damping fence. It is planned to complete the construction works and the installation of equipment by the end of 2018.

    “During the visit we have gained assurance that all the construction works within the territory of the project are carried out strictly in accordance with the time and work schedules, as well as within budget. We will continue to carefully follow the work progress to complete everything within the set terms and ensure that the terminal is fully prepared for the handling of coal and other bulk cargo starting from next year and complies with the highest environmental protection standards”, Ansis Zeltiņš, CEO of the Freeport of Riga, highlighted.

    In caring for the observance of environmental protection standards and the quality of life of the people residing around Krievu Island, a 23m-high dust fence with a length of more than 2 kilometres will be constructed in the territory of the Krievu Island Terminal, which will effectively dampen the wind, preventing coal dust from spreading to the environment. For the construction of the wind fence in the territories of the two stevedoring companies, the construction of foundation piles is currently being carried out. In total, the majority of the planned pile construction work has been carried out at a depth of 24-28 metres. In order to ensure the optimal reduction of wind strength inside the fence and restricting the spread of dust outside the fence, the fence screen material has been selected and will be soon supplied to Krievu Island. The most important function of the wind fence is to effectively dampen the effects of the dominating winds on coal piles, preventing coal dust from blowing into the air and ending up in the environment.

    To free the centre of Riga from coal cargo and transfer the handling of coal to the new terminals equipped with modern technologies on Krievu Island, in 2012 the Freeport of Riga Authority commenced the project “Development of Infrastructure on Krievu Island for the Transfer of Port Activities from the City Centre”. On 31 December 2015, the construction of the principal infrastructure of the Krievu Island Terminal was completed, within which 4 deep-water piers (vessel draft 15.5 m) with the combined length of 1,180 metres and the necessary access roads and engineering and technical infrastructure were constructed.

    Concurrently, in September 2017, for the purposes of carrying out works on the construction of the additional infrastructure commenced by the Freeport of Riga Authority, stevedoring companies constructed administrative and technological buildings, as well as installed special-purpose equipment for coal handling, crushing, transportation and loading onto ships.


2024 April 16

18:04 HD KSOE attains 73% of annual order target in 100 days
17:31 Anglo-Eastern buys Euronav ship manager
17:06 Navig8 takes delivery of the second of six newbuild MRs with emission reducing technology
16:38 IMO’s Facilitation Committee tackles digitalization and autonomous shipping
16:12 World’s largest car carriers ordered with MAN Energy Solutions propulsion package
15:46 Hapag-Lloyd and Seaspan to retrofit five vessels to methanol propulsion
14:13 Asyad Shipping and OQ8 successfully complete first-of-its-kind blended crude oil delivery from Mina Al Fahal to Duqm Refinery
13:54 Hapag-Lloyd unveils its new Strategy 2030
13:14 Singapore aims for over 1 mln tons of low-carbon methanol bunker supply by 2030
12:43 Trafigura to commercially deploy Daphne Technology’s PureMetrics on LNG carrier for precise MRV and optimisation of GHG emissions
12:15 All 12 people rescued from fire on board Tanzanian-flagged cargo ship in Singapore waters
11:49 Drydocks World steel cutting ceremony marks start of UK Norfolk Vanguard Offshore Wind Platforms project
11:23 North Pacific Green Corridor Consortium aims to decarbonize transportation corridor between Canada, Japan and South Korea
10:48 Wartsila offers new high-performance thruster and propulsion control solution package
10:25 Port of Long Beach container volume up 8.3% to 654,082 TEUs in March 2024
09:58 Kalypso Offshore Energy signs LOI with Royal IHC

2024 April 15

18:04 Container shipping costs of S. Korea-EU route surge 40 pct amid Red Sea crisis
17:21 HMM to expand container ship fleet by 2030
17:09 Singapore retains its position as the world's leading maritime city
16:47 Iran says MSC Aries vessel seized for 'violating maritime laws'
16:24 ICTSI gets PPA OK to operate Iloilo Port
15:21 DEME’s offshore installation vessel ‘Orion’ successfully completes the near 15 MW turbine foundation installation project in Scotland and heads to US
14:55 Meriaura orders two biofuel powered 6750 DWT cargo vessels from Royal Bodewes shipyard
14:35 Methanol-fuelled MAN 21/31DF-M GenSet secures first propulsion order
13:32 Port of Valencia export freights grow by 2.13% in March 2024
12:48 Seatrium and Shell inks MOU to further collaborate on floating production systems
12:24 Seaspan launches second LNG bunkering vessel to deliver low-carbon energy solutions to the West Coast
11:57 Japan's 1st coastal module carrier to transport offshore wind turbine foundation components
10:36 EST-Floattech to provide the battery system for the purpose-built electric-landing utility vessel

2024 April 14

16:02 Shanghai's ship exports see considerable growth in Jan-Feb
14:13 Stena Drilling secures 1-well firm programme with Energean for Stena Forth in Morocco
12:07 GSBN: Lack of digital processes in shipping complicates decarbonization game
10:22 Panama Canal expects return to normal transit capacity by 2025

2024 April 13

15:04 Subsea7 awarded contract in the Gulf of Mexico
13:51 Shanghai Electric’s 'ZHI ZHEN 100' excels thorough offshore equipment test
11:18 WSC: Updated version released of “Prevention of Pest Contamination of Containers: Joint Industry Guidelines for the Cleaning of Containers”
09:43 Financiers and insurers ready to support electrification of the domestic harbour craft sector

2024 April 12

18:02 The first LNG bunkering operation performed at Klaipeda Port
17:32 Nexans announces keel laying ceremony for the CLV vessel
17:19 Arctia to map offshore wind farm area in Norway
17:17 SBM Offshore to construct and install FPSO Jaguar
16:46 OOIL's revenue decreases by 9% in Q1 2024
16:13 Wan Hai Lines holds ship naming ceremony for new vessels
14:45 Oil exports from Russia's Baltic ports set to rise 5% in April - Reuters
12:49 MABUX: Bunker Outlook, Week 15, 2024.
11:41 PaxOcean Group starts construction of the first all-electric tug and supply boat
11:27 MOL inaugurates the largest green hydrogen plant in Central and Eastern Europe
10:58 NYK set to achieve world's first truck-to-ship fuel ammonia bunkering

2024 April 11

18:03 INFODAS granted world’s first type approval for software-defined data diode
17:31 The Maritime and Port Authority of Singapore receives 19 proposals to support early adopters of electric port vessels
17:03 Japanese joint venture explores MAN B&W 60-bore ammonia engine for bulker
16:45 WTO forecasts rebound in global trade but warns of downside risks
16:02 Hitachi Zosen Corporation, MOL and Yanmar Power Technology achieve a 93.8% reduction in methane slip from LNG-powered vessels
15:42 MOL holds naming and launching ceremony for the 1st LNG-fueled ferry on Oarai-Tomakomai route
15:18 Bahamas port goes electric with Konecranes Gottwald Generation 6 Mobile Harbor Crane
14:45 Mediterranean shipwreck kills at least 8 migrants, dozens rescued
14:28 Siem Offshore announces sale of 9 vessels to majore shareholder
14:23 Russia begins diesel exports to Sudan, LSEG data shows
13:44 JSI Alliance completes scope in Basrah Refinery Upgrading Project
13:12 MITSUI to jointly develop ammonia fueled bulk carriers with five partners
12:32 Kongsberg Maritime to supply Promas propulsion systems for the USCG’s new OPC programme
10:54 CWS Airfin350 receives AiP from Bureau Veritas
10:22 Nesec contributes to the funding of maritime battery developer EST-Floattech
09:52 Finnlines launches new service between Malmo and Swinoujscie

2024 April 10

18:20 First companies confirmed for innovation hub NextGen Demo in the port of Antwerp-Bruges
17:01 ClassNK issues type approval certificate for CBM management software developed by Samsung Heavy Industries
16:40 DNV awards AIP to HMD for new ammonia-powered LPG carrier designs
16:09 Kongsberg to provide maritime surveillance services to Norway
14:42 NYK completes basic design process using only 3D drawings for new oceangoing vessel
14:26 Japan's 1st hydrogen and bio fuel hybrid passenger ship 'Hanaria' starts service in Kitakyushu