  • Crucial progress in construction of the second stage of the Krievu Island Terminal
  • 2018 June 26 10:30

    Crucial progress in construction of the second stage of the Krievu Island Terminal

    Last week, on 20th of June, Ansis Zeltiņš, CEO of the Freeport of Riga, and representatives from ACB, general contractor for the construction of the second stage of the Krievu Island Terminal project, familiarised Members of the Freeport of Riga Board with the progress in the construction of the second stage of the Krievu Island project during an on-site visit. Freeport of Riga says members of the Board gained confidence that the construction of additional infrastructure would be carried out according to the work plan and more than half of the total construction work had been completed in the territories of stevedoring companies.

    “What we saw today strengthens our confidence that the principal goal of the Krievu Island project will be successfully achieved, and the complete transfer of bulk cargo operations from the right shore of the Daugava — Andrejsala and Eksportsala territories — to Krievu Island will be carried out as planned. The handling of cargo in one of the most advanced multi-functional terminals in the Baltic Sea Region will start as planned — in 2019”, Andris Ameriks, Chairperson of the Freeport of Riga Board, highlighted.

    So far within the framework of the second stage, the construction of the gas pipeline and other underground communications, as well as platforms and railway, has been completed. Works on Krievu Island are being carried out according to the planned schedule of construction works. For example, the construction of power supply cables has practically been completed in the territory of SIA STREK, whereas work on the construction of a water supply system are being actively carried out in the territory of SIA Riga Coal Terminal. Concrete-slab and asphalt cover is currently being constructed for cargo platforms. Stevedoring companies at the site are installing technological equipment and constructing automatic wagon supply systems. The stevedoring companies will install mobile technological equipment for handling cargo. Likewise, works are being carried out on construction of a wind-damping fence. It is planned to complete the construction works and the installation of equipment by the end of 2018.

    “During the visit we have gained assurance that all the construction works within the territory of the project are carried out strictly in accordance with the time and work schedules, as well as within budget. We will continue to carefully follow the work progress to complete everything within the set terms and ensure that the terminal is fully prepared for the handling of coal and other bulk cargo starting from next year and complies with the highest environmental protection standards”, Ansis Zeltiņš, CEO of the Freeport of Riga, highlighted.

    In caring for the observance of environmental protection standards and the quality of life of the people residing around Krievu Island, a 23m-high dust fence with a length of more than 2 kilometres will be constructed in the territory of the Krievu Island Terminal, which will effectively dampen the wind, preventing coal dust from spreading to the environment. For the construction of the wind fence in the territories of the two stevedoring companies, the construction of foundation piles is currently being carried out. In total, the majority of the planned pile construction work has been carried out at a depth of 24-28 metres. In order to ensure the optimal reduction of wind strength inside the fence and restricting the spread of dust outside the fence, the fence screen material has been selected and will be soon supplied to Krievu Island. The most important function of the wind fence is to effectively dampen the effects of the dominating winds on coal piles, preventing coal dust from blowing into the air and ending up in the environment.

    To free the centre of Riga from coal cargo and transfer the handling of coal to the new terminals equipped with modern technologies on Krievu Island, in 2012 the Freeport of Riga Authority commenced the project “Development of Infrastructure on Krievu Island for the Transfer of Port Activities from the City Centre”. On 31 December 2015, the construction of the principal infrastructure of the Krievu Island Terminal was completed, within which 4 deep-water piers (vessel draft 15.5 m) with the combined length of 1,180 metres and the necessary access roads and engineering and technical infrastructure were constructed.

    Concurrently, in September 2017, for the purposes of carrying out works on the construction of the additional infrastructure commenced by the Freeport of Riga Authority, stevedoring companies constructed administrative and technological buildings, as well as installed special-purpose equipment for coal handling, crushing, transportation and loading onto ships.




2021 December 6

18:37 The Port of Bergen changes the name of the Hurtigruten terminal
18:22 Preliminary results of Volga Basin cargo traffic – 41.39 million tonnes
18:14 Equinor invests in battery storage company
17:55 ENGIE and Masdar form US$5 billion strategic alliance to drive UAE’s green hydrogen economy
17:38 Moody’s upgrades Global Ports’ rating to Ba1 with stable outlook
17:16 Solstad Offshore announces long-term contracts in Brazil
16:44 Port of HaminaKotka cargo turnover in 11M’2021 fell by 1.5%
16:20 TezMedz and Tabiyat.pk signs contract with Maersk for integrated cold chain solutions
16:05 “K” Line obtains VSPS regarding Australian quarantine for car carrier
15:55 LR and InterManager share new insights into the causes of lifeboat accidents
15:50 Sea Port of Saint-Petersburg upgrades its infrastructure
15:14 Diana Shipping announces the acquisition of a resale new-building Capesize dry bulk vessel
14:57 Arctia’s IB Otso sets off for the Bay of Bothnia as the season’s first icebreaker
14:35 Cargo traffic within Azov-Don Basin of Russia’s IWWs fell by 14.2% in 2021
14:03 Jan De Nul receives the transport & installation for Vesterhav Nord & Syd wind farm in Denmark
13:48 Onezhsky Shipyard lays down sixth crab catching ship for Russian Crab Group
13:16 DOTr, PPA unveil P316 million Zamboanga port expansion
12:42 Cargo transportation by Volga-Don Canal decreased by 10.6% in navigation season 2021
12:14 New technology risks must be tackled despite decade of progress in ship safety, warns DNV
11:57 Сruise ship Peotr Veliky made first technological voyage
11:38 Mohammed bin Rashid and Mohamed bin Zayed launch UAE Rail Program
11:14 IAA PortNews’ summary of previous week news
10:51 MABUX: No firm trend on Global bunker market on Dec 06
10:20 New shipyard for large-capacity facilities should be built in Russia – opinion
09:29 Crude oil market sees recovery of prices
09:12 Baltic Dry Index as of December 3

2021 December 5

15:03 GasLog Ltd. places order at DSME for four 174000m3 gas carriers
13:27 USCG holds annual SaR exercise off Maui
12:33 Port of Felixstowe tops 100 million TEU
11:51 Vuosaari fairway deepening project completed on schedule, safely and under budget
10:47 New regional technology clusters in WA and Qld driving growth in Australia’s hydrogen sector

2021 December 4

15:21 MOL and Flotation Energy to explore offshore floating wind in Japan
14:51 Sembcorp Marine's LMG Marin to design world’s first zero-emission fuel tanker
13:09 USCG, royal Turks and Caicos Islands Police Force sign MOU
12:34 The Hurtigruten terminal has been renamed Jektevik terminal
11:02 Port of Rotterdam Authority embarks on partnerships with three promising maritime companies

2021 December 3

18:26 Hydrographic Company set to establish Center of Engineering and Technical Expertise
18:07 ABP Humber complete oil spill incident management exercise
17:52 Wärtsilä OPTI-DP Engagement Tool supporting the marine industry to configure optimised propulsion arrangements for DP vessels
17:45 Ocean Network Express conducts a joint crisis management drill with Seaspan Corporation
17:40 Transport Strategy of Russia until 2030 with forecast until 2035 published on official portal
17:22 MSC adds Hamburg to its feeder service „Baltic Loop 3“
17:02 Vyborg Shipyard launches KMT01 trawler named Kara Sea
16:32 South African minister visits Port of Rotterdam to discuss hydrogen exports
16:05 PD Ports contracts Konecranes to convert four RTGs to electric
15:31 Four Jones Act CTVs built to ABS Class to support U.S. offshore wind development
15:17 ABS, NYK, MTI and WinGD team-up to verify design with modeling and simulation
14:03 Jurong Port joins the Castor Initiative
13:30 ABS awards sustainability notations to two Harvey Gulf vessels
13:04 Kapitan Dranitsyn and Admiral Makarov icebreakers reinforced icebreaker group on NSR
12:57 Royal IHC delivers key components for “R.B. Weeks” to Weeks Marine
12:42 Icebreaker assistance season begins in White Sea waters
12:17 Sailing practice of 2021 on Mir sailing ship successfully completed
11:21 NCSP Group's consolidated revenue for 9M’2021 rose by 9.3%
10:53 Foreign contractors can be involved to build LNG-powered icebreakers for Arctic
10:38 MABUX: Bunker prices may demonstrate multidirectional changes with tendency to grow on Dec 3
10:29 The Korean Register publishes guidance for containers loading on bulk carriers
10:20 MSU-1 to perform reconstruction of Gorodetsky hydrosystem locks
09:57 Annual repair dredging in Gulf of Ob from 2023 estimated at 5 million cbm
09:35 Crude oil prices rise on OPEC+ decision to keep oil output increase in January